On 15 September 2023, APA Group submitted additional information in support of its application to convert the Basslink interconnector from a market network service provider to a prescribed transmission service. APA Group also submitted its revenue determination proposal. The proposal and supporting materials are included below.
On this page
Regulatory proposal
Basslink - Conversion and transmission determination 2025-30 - 15 September 2023
Basslink - Conversion and transmission determination - fact sheet - 15 September 2023
Basslink - Conversion and transmission determination - overview - 15 September 2023
Regulatory proposal update - October 2024
Basslink - Update to Pricing methodology - Conversion and transmission determination 2025-30 - October 2024
Basslink - Update to RAB - Conversion and transmission determination 2025-2030 - October 2024
Basslink - Update to Attachment 4.1 Pricing Methodology - September 2024
Confidentiality claims
Basslink - Attachment 14 - Confidentiality claims register proposal - 15 September 2023
Models
Basslink - Attachment 2.2 - Long term cost model - 15 September 2023
Basslink - Attachment 5.1a - RAB calculation - 15 September 2023
Basslink - Attachment 7.7 - Forecast capital expenditure model - 15 September 2023
Basslink - Attachment 12 - Worksheet historical and forecast - 15 September 2023
Models Update - April 2024
Models Update - July 2024
Models Update - October 2024
Basslink - Attachment 5.1a - RAB Calculation - Updated - October 2024
Supporting information
Basslink - Attachment 1 - Conversion application - 15 September 2023
Basslink - Attachment 2 - Net market benefits - 15 September 2023
Basslink - Attachment 3 - Stakeholder engagement summary - 15 September 2023
Basslink - Attachment 3.1 - Engagement summary report - 15 September 2023
Basslink - Attachment 3.2 - Consumer engagement - consolidated report - 15 September 2023
Basslink - Attachment 3.3 - RRG independent report - 15 September 2023
Basslink - Attachment 4 - Revenue and pricing methodology - 15 September 2023
Basslink - Attachment 4.1 - Pricing methodology - 15 September 23
Basslink - Attachment 5 - Regulatory asset base - 15 September 2023
Basslink - Attachment 6 - Asset classes, asset lives and depreciation - 15 September 2023
Basslink - Attachment 7 - Forecast capital expenditure - 15 September 2023
Basslink - Attachment 7.1 - Life cycle management plan - 15 September 2023
Basslink - Attachment 7.2 - Control protection system business case - 15 September 2023
Basslink - Attachment 7.4 - Physical security business case - 15 September 2023
Basslink - Attachment 8 - Forecast operating expenditure - 15 September 2023
Basslink - Attachment 8.4 - Cost allocation methodology - 15 September 2023
Basslink - Attachment 9 - Rate of return - 15 September 2023
Basslink - Attachment 10 - Incentive arrangements - 15 September 2023
Basslink - Attachment 11 - Cost pass throughs - 15 September 2023
Basslink - Attachment 13 - Network Capability Incentive Parameter Action Plan - 15 September 2023
Basslink - Attachment 15 - Directors certification of reasonableness - 15 September 2023
Additional supporting information
On 20 October 2023 Basslink has submitted Attachment 17 - Negotiating Framework 2025-2030 in support of its proposal.
Consultant reports
Basslink - Amplitude - Attachment 1.1 - Asset condition report - 15 September 2023
Basslink - EY - Attachment 2.1 - Report to APA - Basslink benefits - 15 September 2023
Basslink - Amplitude - Attachment 5.2 - Optimised replacement cost and alternatives - 15 September 2023
Basslink - BIS Oxford Economics - Attachment 8.2 - Labour escalators report - 15 September 2023
Basslink - ACIL Allen - Attachment 8.3 - Response vessel customer benefits - 15 September 2023
Negotiated transmission service criteria
By virtue of clause 11.98.8 of the NER, the provisions for negotiated transmission services in version 109 of the NER continue to apply in Victoria. This means that as part of our transmission determination for Basslink we must make a decision on the Negotiated Transmission Service Criteria (NTSC) to be applied by Basslink in negotiating terms and conditions of access for its negotiated transmission services.
Our proposed NTSC for Basslink are available below. Submissions on the proposed NTSC together with submissions on Basslink's proposal, closed 16 February 2024.
Proposed negotiated transmission service criteria for Basslink - November 2023
Issues paper
On 10 November 2023, we released an Issues Paper highlighting some of the key elements of Basslink's proposal. Submissions closed on 16 February 2024 and are available on our website below.
AER - Issues paper - Basslink - conversion and revenue determination 2025-30 - November 2023
Stakeholder forum
On 22 November 2023, we hosted an online public forum where stakeholders asked questions about APA Group's conversion application and revenue proposal for Basslink before submissions closed on 16 February 2024. Presentations were delivered by the AER and APA Group. The presentation slides are available below.
AER - Public Forum - Combined presentation pack - Basslink transmission determination 2025-30 - 22 November 2023
Submissions
Interested stakeholders were invited to make a submission on Basslink's proposal, the proposed Negotiated Transmission Service Criteria, and our Issues Paper.
Submissions closed on Friday, 16 February 2024 and are available below.
TasNetworks - Submission on Basslink Issues Paper - Determination 2025-30 - February 2024
AEMO - Submission on Basslink Issues Paper - Determination 2025-30 - February 2024
APA - Submission on Basslink Issues Paper - Determination 2025-30 - February 2024
Aurora Energy - Submission on Basslink Issues Paper - Determination 2025-30 - February 2024
Hydro Tasmania - Submission on Basslink Issues Paper - Determination 2025-30 - February 2024
Tasmanian Government - Letter to the AER - Submission on Basslink Issues Paper - Determination 2025-30 - February 2024
Tasmanian Government - Submission on Basslink Issues Paper - Determination 2025-30 - February 2024
TMEC - Submission on Basslink Issues Paper - Determination 2025-30 - February 2024
Late submissions
The following submission was received after submissions closed on 16 February 2024.