Owner
Queensland Government
Covered by regulation
Yes
Source
State of the Energy Market 2014
Current regulatory period: 1 July 2010 - 30 June 2015
Customer numbers |
Line length (km) |
Maximum demand 2012-13 (MW) |
Asset base June 2013 ($million) |
1 359 712 |
51 781 |
5 029 |
10 197 |
Decisions
Energex’s South East Queensland storms cost pass through application
Energex proposed new network prices to apply to its Queensland network for 2024–25.
Energex submitted to the AER an annual pricing proposal for its Queensland distribution network for the period 1 July 2023 to 30 June 2024.
Energex submitted to the AER an annual pricing proposal for its Queensland distribution network for the period 1 July 2022 to 30 June 2023.
Type
Cost allocation methods
Reports
Our second annual report analysing distribution network performance in providing services to customers who export electricity back into the grid.
Energex Network information - RIN responses
Our network performance reports presents our latest electricity and gas networks performance within regulatory frameworks.
Annual report analysing distributor performance in providing services to customers who export electricity back into the grid.
Distribution performance data 2006-2018