Overview

Draft decision

On 29 November 2024, we released our draft decision on Jemena Gas Networks (NSW) ('JGN') access arrangement proposal for the 2025–30 period commencing 1 July 2025.

For our draft decision, there is no Attachment 1 Services covered by the access arrangement and this component is covered in the Overview.

Consultant reports

We commissioned the following report, which we took into account when making our draft decision for JGN.

ACIL Allen - JGN demand review report - November 2024

Download
Authors
ACIL Allen
Content type
Document

Stakeholder forum - draft decision

A public forum was held on Wednesday, 11 December 2024 at 1-2.30pm (AEDT) as an opportunity for interested stakeholders to ask questions about our draft decision.  

At the public forum we presented on our draft decision and had presentations from the Justice and Equity Centre, St. Vincent De Paul, the AER's Consumer Challenge Panel and Jemena Gas Networks. 

The combined presentation pack is published below.

Submissions

-

Interested stakeholders are also invited to make submissions on both our draft decision and JGN’s revised proposal (once submitted) by Friday, 14 February 2025. 

Submissions can be sent to JGN2025ataer [dot] gov [dot] au (JGN2025[at]aer[dot]gov[dot]au).

Alternatively, submissions can be sent to:
Arek Gulbenkoglu
General Manager 
Australian Energy Regulator
GPO Box 1313 
Canberra ACT 2601

Submissions should be in Microsoft Word or another text readable document format.

We prefer that all submissions be publicly available to facilitate an informed and transparent consultative process. We will treat submissions as public documents unless otherwise requested. For more information see the ACCC/AER Information policy.