Indicative timetable

Indicative dates for key milestones in the decision making process
MilestoneDate*
JGN submits reference service proposal28 June 2023
AER makes reference service proposal decisionDecember 2023
JGN submits access arrangement proposal28 June 2024
AER publishes issues paperAugust 2024
AER holds public forumSeptember 2024
Submissions on proposal and issues paper closeSeptember 2024
AER publishes draft decisionNovember 2024
JGN submits revised proposalJanuary 2025
Submissions on draft decision and revised proposal closeFebruary 2025
AER publishes final decisionby May 2025

*Please note this timeline is subject to change.

Reference service proposal

On 28 June 2023, JGN submitted its reference service proposal for the 2025–30 access arrangement period.

Jemena Gas Networks - Reference Service Proposal - 28 June 2023

Download
Authors
Jemena Gas Networks (NSW) Ltd
Content type
Document

Submissions

-

Submissions on JGN's reference service proposal closed on 1 August 2023.

Red Lumo - Jemena Gas Networks Reference Services Proposal - August 2023

Download
Authors
Red Energy & Lumo Energy
Content type
Document

Final decision

In November 2023, the AER made its final decision on JGN's reference service proposal. Our final decision is to approve JGN's proposed transportation and ancillary reference services. Details are set out in the AER final decision paper.

AER final decision - JGN reference service proposal 2025-30

Download
Authors
AER
Content type
Document