Owner
Publicly listed company (Singapore Power International 31%, State Grid Corporation 20%)*
Covered by regulation
Yes
Source
State of the Energy Market 2014
Current regulatory period: 1 April 2014 - 30 March 2017
Line length (km) |
Electricity transmitted 2013-13 (GWh) |
Asset base June 2013 ($million) |
6 573 |
49 056 |
2 414 |
On 4 August 2014, SP AusNet was rebranded as AusNet Services.
Decisions
The AER will make a determination of the maximum amount of revenue that AusNet Services can earn from customers over the period 1 April 2027 to 31 March 2032.
AusNet Services submitted a cost pass through application seeking to recover the costs it has incurred as a result of the 13 February 2024 storm in Victoria.
AusNet Services submitted to the AER an annual pricing proposal for its Victorian distribution network for the period 1 July 2023 to 30 June 2024.
Type
Cost allocation methods
Type
Cost allocation methods
On 28 January 2022 the AER published its final decision on the revenue AusNet Services can recover from its customers in the 2022–27 regulatory period.