On 23 February 2018, AusNet Services submitted an application to the AER under clauses 6A.7.3 and 11.6.21 of the NER for a negative pass through of easements land tax for the amount of $4,422,331 ($nominal, GST exclusive). The AER has determined that the proposed pass through amount is appropriate and meets the rule requirements. We consider that all of this pass through amount should be passed through to AusNet Services' Transmission Network Users in 2018–19.