On 24 January 2020, the AER published its determination on whether the preferred option identified in the SAET RIT-T satisfies the RIT-T.
Determination
AER - Determination - SA Energy Transformation RIT-T - 24 January 2020
Download
Content type
Document
Supporting information
Frontier Economics - SAET RIT-T assessment - Final Report - 20 December 2019
Download
Content type
Document
ElectraNet - Additional modelling and sensitivity analysis for SAET RIT-T- 16 January 2020
Download
Content type
Document
AEMO - Assumptions for South Australian GPG in the 2018 ISP - August 2019
Download
Content type
Document
Update - ElectaNet request to AER
On 14 September 2020 ElectraNet requested the AER accept that ElectraNet has demonstrated that there has not been a material change in circumstances as described in cl. 5.16.4(z3) and (z4) of the National Electricity Rules (NER). On 28 September 2020, we provided a response to ElectraNet’s request. ElectraNet and TransGrid have subsequently lodged contingent project applications to the AER.
ElectraNet - Letter to AER - Project EnergyConnect updated CBA - 14 September 2020