Our approval role#

The AER is required by the National Electricity Rules (NER) to assess applications by network service providers to amend their regulatory revenue determination to include the revenue required for a contingent project.

Contingent projects are major network infrastructure assets which have been flagged in long-term investment plans.

When a network business has met the requirements to request cost recovery from consumers for one of these projects, it submits a contingent project application to us for approval.

We undergo a rigorous assessment process to ensure that consumers pay no more than is needed to build the new infrastructure.

Our decisions#

View the collection of contingent project decisions.

Results#

Ausgrid Increased Customer Demand Requirements in the Macquarie Park Area Contingent Project

Ausgrid’s contingent project application requesting a revenue increase to fund its Wallumatta substation.
Type
Contingent projects
Sector
Electricity
Status
Open

TasNetworks North West Transmission Developments Stage 1 – Early Works Contingent Project

On 10 October 2024, TasNetworks submitted its contingent project application seeking to increase its revenue to fund early works on NWTD stage 1 early works.
Type
Contingent projects
Sector
Electricity
Status
Open

Transgrid HumeLink contingent project stage 2

Transgrid HumeLink contingent project stage 2
Type
Contingent projects
Sector
Electricity
Status
Current

Transgrid VNI West contingent project application stage 1 early works

Transgrid Victoria to NSW Interconnector West (VNI West) contingent project application stage 1 early works
Type
Contingent projects
Sector
Electricity
Status
Current

Transgrid - Humelink early works contingent project - stage 1 part 2

The AER's decision in relation to Transgrid's Humelink stage 1 part 2 contingent project application.
Type
Contingent projects
Sector
Electricity
Status
Current

Transgrid - Humelink early works contingent project - stage 1 part 1

The AER's decision relating to the Humelink early works contingent - stage 1 part 1.
Type
Contingent projects
Sector
Electricity
Status
Current