Overview

Sector
Electricity
Segment
Wholesale
Region
New South Wales
Status
Current
Categories
Notice of closure
Classes
Exempt
Notice status
Current notice
Effective date
Commencement date
Applicants
AGL Macquarie Pty Limited
AER reference
AER212749

On 16 July 2021, the AER published its final decision, approving AGL Macquarie Pty Limited's (AGL) application for exemption from notice of closure requirements in the National Electricity Rules.

On 30 April 2021, AGL submitted an application to amend the closure date for Liddell power station unit 3 (LD03). The application sought to swap the closure dates of Liddell power station unit 4 (LD04) and unit 3 (LD03) to improve the operation of Liddell in its transition to close in 2023.

After assessing the recent performance of LD03 and LD04, and consultation with the Australian Energy Market Operator, the AER has approved the request on the basis that swapping the closure dates of the two units should improve the reliability of the Liddell power station in its last year of operation.

Under the exemption, LD03 will close on 1 April 2022. AGL will then delay the closure of LD04 to 1 April 2023.