Project timeline

Overview

Type
Sector
Electricity
Segment
Wholesale
Region
Australian Capital Territory
New South Wales
Queensland
South Australia
Tasmania
Victoria
Status
Current
Date initiated
Effective date
Date completed
Categories
Exemption guideline
AER reference
64847

From 1 September 2019, generators are required to provide at least 42 months' advance notice of their intention to close, unless we grant an exemption. We are required to publish guidelines for how we intend to handle applications for exemption, and what information applicants will be required to submit. We published our exemption guideline on 29 August 2019.

Minor, administrative changes were made to this guideline in October 2024 to account for the Integrating Energy Storage Systems rule change.

Background

In developing the exemption guideline we published a draft on 7 June 2019 that sought stakeholder comment on our proposed guideline. Three submissions were received. Prior to developing the draft guideline, on 1 March 2019 we also published an issues paper that sought comment on key issues related to the guideline’s development. Seven submissions were received.

Key Documents