Overview

Final decision - Decision

On the 1 October 2003, the ACCC released its decision in relation to its assessment of Murraylink application.

AER Decision - 1 October 2003

Download
Content type
Document

Further final decision - Murraylink revenue cap revocation and substitution 2004

On 2 February 2004 the ACCC received an application from the Murraylink Transmission Company (MTC) under clause 6.2.4 of the national electricity code for the revocation and substitution of its revenue cap to correct errors made in its decision of 1 October 2003.

On 31 March 2004 the ACCC decided to revoke MTC's revenue cap and to make a new revenue cap in the form proposed by MTC. The reasons for the decision are set out in the revocation and substitution letter to MTC dated 7 April 2004.