Sector
Electricity
Segment
Transmission
Region
Tasmania
Victoria
Interconnector
Status
Open
Commencement date
Regulatory period
-
AER reference
AER23007164

On 31 March 2023 the AER received a submission from Tasmanian intending transmission network service provider Marinus Link Proprietary Limited, requesting the AER:

  • commence a process for making a transmission determination relating to proposed Marinus Link interconnector, and
  • establish a modified determination process to apply when making the transmission determination.

On 1 June 2023 the AER published its decision to commence a revenue determination process for the Marinus Link interconnector and the Commencement and Process Paper outlining the process that will apply for this determination.

Commencement and Process Paper and RIT-T Update

On 16 February 2024, Marinus Link wrote to the AER requesting amendments to the Commencement and Process Paper and provided a RIT-T update. 

On 15 March 2024, the AER published its decision to approve the requested amendments and an updated Commencement and Process Paper

On 30 October 2024, Marinus Link wrote to the AER requesting further amendments to the Commencement and Process Paper.

On 3 December 2024, the AER decided to amend the Marinus Link determination process and publish the revised Commencement and Process Paper.

Revenue Proposal

On 29 November 2024 Marinus Link submitted its Stage 1 - Part B (Construction Cost) Revenue Proposal to the AER.

Background

The proposed Marinus Link interconnector will comprise two 750 MW high voltage direct current (HVDC) cables running 255km undersea and 90km underground HVDC cables between Burnie, Tasmania and Latrobe Valley, Victoria. 

Key Documents