Overview

Draft decision

On 26 October 2017, we released our draft decision on ElectraNet's transmission determination for the 2018–23 regulatory control period.

We also released a Fact Sheet to accompany and summarise our draft decision. The purpose of this Fact Sheet is to make our decision accessible to a wide-ranging consumer audience.

AER - Draft decision - Overview - 26 October 2017

Download
Authors
AER
Content type
Document

AER - Fact Sheet - 26 October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 1 - Maximum allowed revenue - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 2 - Regulatory asset base - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 3 - Rate of return - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 5 - Regulatory depreciation - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 6 - Capital expenditure - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 7 - Operating expenditure - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 8 - Corporate income tax - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 12 - Pricing methodology - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 13 - Pass through events - October 2017

Download
Authors
AER
Content type
Document

AER - Attachment 14 - Negotiated services - October 2017

Download
Authors
AER
Content type
Document

Consultant reports

Reports commissioned by the AER in preparing our draft decision for ElectraNet:.

Partington and Satchell - Advice on AER equity beta update - September 2017

Download
Authors
Partington and Satchell
Content type
Document

Submissions

-

We invited energy consumers and other interested parties to make submissions on our draft decision by 29 January 2018.

Stakeholder forum

We held a pre-determination conference on our draft decision on Monday 6 November 2017 in Adelaide.