Overview

Sector
Gas
Segment
Transmission
Region
Queensland
Status
Historical
Commencement date
Regulatory period
-

On 4 June 2002 the Australian Competition and Consumer Commission (ACCC) released its final approval of the access arrangement proposed by Epic Energy for its Ballera to Wallumbilla Pipeline System, also known as the South West Queensland Pipeline (SWQP).

The SWQP was the subject of a Queensland Government derogation which prevented the ACCC from reviewing the reference tariffs and related areas of the access arrangement until 2016. This meant that major aspects of the access arrangement were not subject to consideration by the ACCC. In particular, the final decision contains no assessment of reference tariffs or reference tariff policy.

Key Documents

Epic Energy - Revised access arrangement - 8 February 2002

Download
Authors
Epic Energy (Qld) Pty Ltd
Content type
Document

ACCC - approved access arrangement for SWQP 2002-2004

Download
Authors
Australian Competition and Consumer Commission (ACCC)
Content type
Document

ACCC - Final approval notice - 4 June 2002

Download
Authors
Australian Competition and Consumer Commission (ACCC)
Content type
Document

ACCC - Final decision on SWQP access arrangement - 28 November 2001

Download
Authors
Australian Competition and Consumer Commission (ACCC)
Content type
Document