Overview

Application

On 30 September 2020, ElectraNet and TransGrid submitted final contingent project applications to the AER seeking increases to their allowed revenue in accordance with clause 6A.8.2 of the NER to fund the construction of the South Australia (SA) to New South Wales (NSW) interconnector (Project EnergyConnect).

On 24 November 2020, ElectraNet submitted an update to its contingent project application after reaching agreement with the South Australian Government to undertake a range of early works in order to advance the delivery schedule of the project by 9 months.

Project EnergyConnect involves the construction of a new 860 km 330 kV interconnector between Robertstown in mid-north SA and Wagga Wagga NSW, with an augmentation between Buronga and Red Cliffs in north-western Victoria. This project relates to the preferred network investment option identified through ElectraNet’s South Australian Energy Transformation Regulatory Investment Test for Transmission (RIT-T).

We received two separate applications that together cover the total cost of the project:

  • TransGrid’s application relates to the NSW component of the interconnector and the revenues it seeks to recover from customers in NSW.
  • ElectraNet’s application relates to the SA component of the interconnector and the revenues it seeks to recover from customers in SA.

The AER is required to make a determination on these contingent project applications under clause 6A.8.2 of the NER. 

Indicative timetable

Indicative dates for key milestones in the decision making process
Milestone Date*
Contingent project applications 30 September 2020
Information gathering and consultation process 4-6 weeks
Public submissions due 30 October 2020
AER assessment and decision making 6-8 weeks

*Dates are indicative and subject to change.

Submissions

Interested parties were invited to provide submissions on TransGrid and ElectraNet’s contingent project applications by 30 October 2020. Submissions are now closed. On 24 November 2020, ElectraNet provided a summary response to issues raised in submissions, which is provided below.

Application - TransGrid

On 29 June 2020, TransGrid submitted an initial contingent project application to the AER seeking an increase to its allowed revenue to fund the construction of the NSW component of the project. This application was based on preliminary project cost estimates that were confidential.

On 23 July 2020, we wrote to TransGrid stating that we could not commence the formal public contingent project determination process at that time. This was because TransGrid’s cost estimates were likely to substantially change and were confidential in nature, which meant that the application was not capable of being published in accordance with clause 6A.8.2(c) of the NER.

On 30 September 2020, TransGrid submitted supplementary information that included updated project cost estimates and incremental revenues required to undertake the project. Stakeholders should consider both the June 2020 application and the September 2020 supplementary material when reviewing TransGrid’s contingent project application.

TransGrid - Project EnergyConnect - Principal Application - 29 June 2020

Download
Authors
Transgrid (T)
Content type
Document

TransGrid - Letter to AER - Project EnergyConnect - 30 September 2020

Download
Authors
Transgrid (T)
Content type
Document

Supporting information - TransGrid

TransGrid - A.2 - PEC - Stakeholder Engagement Overview - 30 September 2020

Download
Authors
Transgrid (T)
Content type
Document

TransGrid - A.4 - PEC - Specification and scope BAFO - 30 September 2020

Download
Authors
Transgrid (T)
Content type
Document

TransGrid - A.6 - PEC - Capex Forecast Model - 30 September 2020

Download
Authors
Transgrid (T)
Content type
Document

TransGrid - A.11A - FTI PEC - Wider Benefits Report - October 2020

Download
Authors
Transgrid (T)
Content type
Document

TransGrid - A.13 - PEC - Opex Forecast Model - 20 September 2020

Download
Authors
Transgrid (T)
Content type
Document

TransGrid - A.14 - PEC - Insurance Report - 3 September 2020

Download
Authors
Transgrid (T)
Content type
Document

TransGrid - A.16 - PEC - Summary of model changes - 30 September 2020

Download
Authors
Transgrid (T)
Content type
Document

Transgrid - JLL Report Land Acquisition Costs Revised - 25 August 2020

Download
Authors
Transgrid (T)
Content type
Document

TransGrid - WSP - Biodiversity Memo - 9 September 2020

Download
Authors
Transgrid (T)
Content type
Document

Application - ElectraNet

Supporting information - ElectraNet

ElectraNet - PTRM - September 2020

Download
Authors
ElectraNet
Content type
Document

ElectraNet - Scope of Works - September 2020

Download
Authors
ElectraNet
Content type
Document

ElectraNet - Cost Estimate Report - September 2020

Download
Authors
ElectraNet
Content type
Document

ElectraNet - ACIL Price Impact Analysis - September 2020

Download
Authors
ElectraNet
Content type
Document

Confidentiality claims

TransGrid - Confidentialtiy Claims - 8 October 2020

Download
Authors
Transgrid (T)
Content type
Document

Update - ElectraNet's application

On 24 November 2020, ElectraNet submitted an update to its contingent project application after reaching agreement with the South Australian Government to undertake a range of early works in order to advance the delivery of the project. ElectraNet’s update outlines a revised date for project completion of 31 March 2023, 9 months earlier than previously identified, and a consequential change in the timing of the capital expenditure and revenue required to deliver the project. As a result of these timing changes, ElectraNet’s forecast of total capital expenditure for the contingent project application is slightly reduced to $469 million, and is expected to be incurred entirely within the 2018-23 regulatory control period.

ElectraNet - PTRM - November 2020

Download
Authors
ElectraNet
Content type
Document