Overview

Sector
Electricity
Segment
Transmission
Region
Queensland
Status
Current
Commencement date
Effective date
AER reference
AER23006902

On 19 September 2023, Powerlink wrote to the AER requesting a determination on its 2022–23 network support pass through application. Powerlink’s network support pass through application is in relation to the difference between actual network support payments and the forecast network support payment amount for 2022–23 included in Powerlink’s 2022–27 revenue determination. The AER assessed the application in accordance with clause 6A.7.2(i) of the NER.

The AER determines to approve a positive pass through amount of $866,339.

Key Documents