On 25 August 2023, the AER published its final decision in relation to Transgrid's HumeLink early works stage 1 part 2 contingent project application.
On this page
Final decision
AER - Determination - HumeLink Stage 1 (part 2) - August 2023
AER Determination - HumeLink Stage 1 (part 2)
Download
Content type
Document
AER - Final decision - HumeLink Stage 1 (part 2) - PTRM - 2023-28 - August 2023
AER final decision - HumeLink Stage 1 (part 2) - Post tax revenue model
Download
Content type
Document
AER - Final decision - HumeLink Stage 1 (part 2) - Capex Model - 2023-28 - August 2023
AER final decision - HumeLink Stage 1 (part 2) - Capex Model
Download
Content type
Document
Update - Material change in circumstances provisions
AER advice to Transgrid in relation to material change in circumstances provisions.
AER - Advice to Transgrid in relation to material change in circumstances provisions - 22 August 2023
AER letter to Transgrid
Download
Content type
Document