On 9 January 2020, the AER received an access arrangement revised proposal from Jemena Gas Networks (NSW) Ltd (JGN) for its NSW gas distribution network for the period from 1 July 2020 to 30 June 2025.
Revised proposal
Supporting information
In addition to the files below, JGN has submitted augmentation capex source information relating to a BASIX penetration rate analysis aimed at identifying the approximate number of dwellings which install gas appliances (Attachment 4.8a). This spreadsheet file is too large to upload to our website, but we can provide this file on request. Please email JGNGAAR2020-25aer [dot] gov [dot] au (subject: Revised%20proposal%20-%20request%20for%20JGN%20Attachment%204.8%20Augex%20source%20information%20-%20BASIX%20penetration%20rate%20analysis%20%28file%20too%20large%20to%20upload%20to%20AER%20website%29) (JGNGAAR2020-25[at]aer[dot]gov[dot]au (link sends e-mail)) if you would like a copy of this file.
JGN - Attachment 2.1 - bd infrastructure - Asset Lives Workshop - Outcome Report - January 2020
JGN - Attachment 4.3 - Response to draft decision - Property overheads inflation in capex and RFM - January 2020
JGN - Attachment 4.4 - Matrix of capex supporting information - January 2020
JGN - Attachment 4.7a1 - IT capex source info - IB-SAP migration to S4 - January 2020
JGN - Attachment 4.7a2 - IT capex source info - NPV-SAP Migration to S4 - January 2020
JGN - Attachment 4.7b1 - IT capex source info - IB-Asset Mgmt and GIS enhancement - January 2020
JGN - Attachment 4.7b2 - IT capex source info - NPV-Asset Mgmt and GIS enhancement - January 2020
JGN - Attachment 4.7c1 - IT capex source info - IB-Asset Mgmt and GIS lifecycle - January 2020
JGN - Attachment 4.7c2 - IT capex source info - NPV-Asset Mgmt and GIS lifecycle - January 2020
JGN - Attachment 4.7d1 - IT capex source info - IB-Customer experience hub - January 2020
JGN - Attachment 4.7d2 - IT capex source info - NPV-Customer experience hub - January 2020
JGN - Attachment 4.7e1 - IT capex source info - IB-Enterprise systems lifecycle - January 2020
JGN - Attachment 4.7e2 - IT capex source info - NPV-Enterprise systems lifecycle - January 2020
JGN - Attachment 4.7f1 - IT capex source info - IB-Enterprise systems - Reporting and analysis - January 2020
JGN - Attachment 4.7f2 - IT capex source info - NPV-Enterprise systems - Reporting and analysis - January 2020
JGN - Attachment 4.7g1 - IT capex source info - IB-GIS DBYD - January 2020
JGN - Attachment 4.7g2 - IT capex source info - NPV-GIS DBYD - January 2020
JGN - Attachment 4.7h1 - IT capex source info - IB-Kofax lifecycle - January 2020
JGN - Attachment 4.7h2 - IT capex source info - NPV-Kofax lifecycle - January 2020
JGN - Attachment 4.7i1 - IT capex source info - IB-Metering - Industrial and Commercial - January 2020
JGN - Attachment 4.7i2 - IT capex source info - NPV-Metering - Industrial and Commercial - January 2020
JGN - Attachment 4.7j1 - IT capex source info - IB-Metering - Mass market no access - January 2020
JGN - Attachment 4.7j2 - IT capex source info - NPV-Metering - Mass market no access - January 2020
JGN - Attachment 4.7k1 - IT capex source info - IB-Metering - MDL backend system - January 2020
JGN - Attachment 4.7k2 - IT capex source info - NPV-Metering - MDL backend system - January 2020
JGN - Attachment 4.7l1 - IT capex source info - IB-Reporting server and database lifecycle - January 2020
JGN - Attachment 4.7l2 - IT capex source info - NPV-Reporting server and database lifecycle - January 2020
JGN - Attachment 4.8b - Augmentation capex source info - Malabar Biomethane Project - Options analysis - January 2020
JGN - Attachment 4.8c - Augmentation capex source info - Malabar Biomethane Project - AppB Option2 Drawing - January 2020
JGN - Attachment 4.8e - Augmentation capex source info - Aerotropolis - Letter of support - January 2020
JGN - Attachment 5.3 - Response to draft decision - Opex - January 2020
JGN - Attachment 5.4 - CEPA - Review of AER approach to JGN cost escalators - January 2020
JGN - Attachment 5.5 - BISOE - Review of AER wage forecast comparison - January 2020
JGN - Attachment 5.6 - BISOE - Labour cost escalation forecasts to 2024-25 - January 2020
JGN - Attachment 5.7 - CEG - The cost of arranging debt issues - January 2020
JGN - Attachment 6.2 - Contaminated sites asset classes - January 2020
JGN - Attachment 6.4 - Response to draft decision - Capital base - January 2020
JGN - Attachment 7.2 - Response to draft decision - Inflation - January 2020
JGN - Attachment 8.2 - Response to draft decision - Changes to asset lives for new investments - January 2020
JGN - Attachment 8.3 - Incenta - Using asset lives to manage stranded asset risks - January 2020
JGN - Attachment 8.4 - Prof Cosmo UK - Regulatory decision making and consumer voices - January 2020
JGN - Attachment 8.5 - GPA Engineering - Hydrogen Future Study - January 2020
JGN - Attachment 8.6 - Core - 2019-2070 Scenario based outlook for JGN gas demand - January 2020
JGN - Attachment 8.7 - Mirvac - Planet positive Mirvac plan to reach net positive carbon by 2030 - January 2020
JGN - Attachment 8.8 - EnergyQuest - Running on empty - How to keep NSW fuelled for the future - January 2020
JGN - Attachment 11.1 - Response to draft decision - CESS - January 2020
JGN - Attachment 13.1 - Response to draft decision - Demand - January 2020
JGN - Attachment 13.4 - Core volumes to PTRM - Tariff V - January 2020
JGN - Attachment 15.1 - Response to draft decision - Revisions to 2020-25 AA - January 2020
JGN - Attachment 15.2 - Mark up of 2020-25 AA in response to draft decision - January 2020
JGN - Attachment 15.3 - Response to draft decision - Revisions to the RSA - January 2020
JGN - Attachment 15.4 - Compare of 2015-20 and 2020-25 RSA - January 2020
JGN - Attachment 15.5 - Compare of 2015-20 and 2020-25 RSA - Changes since June 2019 - January 2020
JGN - Attachment 4.8d - Augmentation capex source info - Aerotropolis - Options analysis - January 2020
JGN - Attachment 4.2 - Response to draft decision - Capex - January 2020
Models
Submissions
We invited interested parties to make submissions on both our draft decision and JGN's 2020-25 access arrangement revised proposal by 17 February 2020.
AGL - Submission on JGN 2020-25 access arrangement - 17 February 2020
CCP19 - Submission to the AER on the AER's draft decision and JGN's revised regulatory proposal - 17 February 2020
EnergyAustralia - Submission on JGN 2020-25 access arrangement - 17 February 2020
Energy Networks Australia - Submission on JGN 2020-25 access arrangement - 13 February 2020
Evoenergy - Submission on JGN 2020-25 access arrangement - 10 February 2020
Origin - Submission on JGN 2020-25 access arrangement - 17 February 2020
Submissions - Correspondence
The AER has received correspondence from JGN on issues relevant to its 2020-25 access arrangement revised proposal. This letter appears below.