On 31 March 2023, Evoenergy submitted to the AER an annual pricing proposal for its Australian Capital Territory distribution network for the period 1 July 2023 to 30 June 2024. 

On 27 April 2023, Evoenergy submitted a revised pricing proposal in response to AER queries. This resubmission resulted in minor changes to proposed prices.

On 4 May 2023, the AER approved Evoenergy's annual pricing proposal for the period 1 July 2023 to 30 June 2024. This was after assessing the pricing proposal as compliant with the NER and the AER's 2019–24 regulatory determination.

On 5 May 2023, Evoenergy submitted to the AER a revised pricing proposal document to correct for transcription errors between its model and pricing proposal document. This correction was for consistency with our 4 May decision.