Milestone | Date* |
---|---|
Submissions on proposal | 3 September 2018 |
Draft determination | 26 October 2018 |
Submissions on draft determination close | 23 November 2018 |
Final determination | 18 December 2018 |
*Please note this timeline is subject to change.
Milestone | Date* |
---|---|
Submissions on proposal | 3 September 2018 |
Draft determination | 26 October 2018 |
Submissions on draft determination close | 23 November 2018 |
Final determination | 18 December 2018 |
*Please note this timeline is subject to change.
On 7 June 2018, after lengthy pre-engagement, AGN submitted an application for a determination of future capital expenditure in relation to the Mount Barker gas network extension.
Submissions on the proposed gas network extension to Mount Barker closed 3 September 2018.
The AER commissioned a report from Zincara Pty Ltd on the robustness and overall reasonableness of the application.