Milestone | Date |
---|---|
AER publishes preliminary F&A for SA Power Networks | March 2018 |
Workshop | 17 April 2018 |
Submissions on the preliminary F&A for SA Power Networks close | 27 April 2018 |
AER to publish final F&A for SA Power Networks | July 2018 |
SA Power Networks submits its regulatory proposal to AER | January 2019 |
AER publishes issues paper | 28 March 2019 |
AER holds public forum | 4 April 2019 |
Submissions on regulatory proposal close | May 2019 |
AER to publish draft decision | 8 October 2019 |
AER to hold a predetermination conference | 30 October 2019 |
SA Power Networks to submit revised regulatory proposal to AER | 10 December 2019 |
Submissions on revised regulatory proposal and draft decision close | 15 January 2020* |
AER to publish distribution determination for regulatory control period | 5 June 2020 |
* The date provided is based on the AER receiving compliant proposals. The date may be altered if we receive non-compliant proposals.