Milestone | Date* |
---|---|
AER consultation on need for F&A | 25 May 2018 |
Submissions on need for F&A for Jemena close | 7 June 2018 |
AER issues notice on need for F&A | 30 June 2018 |
AER publishes preliminary F&A | 14 September 2018 |
Workshop | 25 October 2018 |
Submissions on preliminary F&A for Jemena close | November 2018 |
AER to publish final F&A for Jemena | 31 January 2019 |
Jemena submits its regulatory proposal to AER | 31 January 2020 |
AER publishes issues paper and holds public forum | March/April 2020* |
Submissions on regulatory proposal close | May 2020 |
AER to publish draft decision | September 2020 |
AER to hold a predetermination conference | October 2020 |
Jemena to submit revised regulatory proposal to AER | December 2020 |
Submissions on revised regulatory proposal and draft decision close | January 2021* |
AER to publish distribution determination for regulatory control period | 30 April 2021 |
*The date provided is based on the AER receiving compliant proposals. The date may be altered if we receive non-compliant proposals.