Overview

Sector
Electricity
Segment
Distribution
Region
New South Wales
Status
Historical
Commencement date
Regulatory period
-

The AER is required under the transitional provisions within Chapter 11 of the National Electricity Rules (the transitional chapter 6 rules) to make distribution determinations for Endeavour Energy (Integral Energy) in relation to the New South Wales electricity distribution network. On 2 June 2008, Endeavour Energy submitted their regulatory proposal to the AER.

The AER released its final decision and distribution determination on 28 April 2009 for Endeavour Energy (Integral Energy) for the regulatory control period 1 July 2009 to 30 June 2014.

On 25 November 2009 the AER published a further final decision in accordance with the Australian Competition Tribunal's decision.

Key Documents