Overview

Sector
Electricity
Segment
Distribution
Region
New South Wales
Status
Current
Commencement date
Regulatory period
-
AER reference
AER212494

On 31 January 2023, Endeavour Energy submitted its 2024–29 initial revenue proposal to the AER. We published an Issues Paper in March 2023, and held a public forum on April 2023, to assist stakeholders in their consideration of Endeavour Energy's proposal. Submissions and presentations from the online forum are available on our website.

On 28 September 2023, we released our draft decision for Endeavour Energy's initial proposal. We held a public forum on our draft decision on 9 October 2023.

On 30 November 2023, Endeavour Energy submitted its 2024–29 revised proposal.

Interested stakeholders were invited to provide submissions on our draft decision and Endeavour Energy's revised proposal by 19 January 2024 and are available on our website.

Final Decision

On 30 April 2024, we published our final decision on the revenue that Endeavour Energy can recover from its consumers in the 2024-29 regulatory control period.

Background

Endeavour Energy is an electricity distribution network service provider. Its next five year regulatory control period commences on 1 July 2024 to 30 June 2029 (2024–29).

Under the NER, Endeavour Energy is required to submit its regulatory proposal to us by 31 January 2023. However, prior to that date, the NER require us to review the current F&A paper that applies to Endeavour Energy and decide whether to amend or replace it.

In June 2022, Endeavour Energy submitted the methodology it proposes to use to prepare the forecasts of operating expenditure and capital expenditure that form part of its regulatory proposal and the AER, in July 2022, published the final framework for Endeavour Energy.