Overview

Indicative timetable

Indicative dates for key milestones in the decision making process
Milestone Date*
Receive regulatory proposal from ActewAGL 2 June 2008
Public forum on ActewAGL’s regulatory proposal 29 July 2008
Submissions close on ActewAGL’s regulatory proposal 8 August 2008
Release the AER’s draft decision and consultant’s report November 2008
Public forum on the AER’s draft decision December 2008
ActewAGL may lodge revised regulatory proposal January 2009
Submissions close on the draft decision, revised regulatory proposal and consultant’s report February 2009
Release the AER’s final decision April 2009

*Please note this timeline is subject to change.

The AER has engaged consultants to assist with reviewing ActewAGL’s regulatory proposal.