AusNet Services – Cost Pass Through – Easement Land Tax 2025-26
The AER has approved AusNet Services' application for a positive pass through of easement land tax to be recovered in 2025-26.
Type
Cost pass throughs
Status
Current
APA Victorian Transmission System - 2025 tariff variation notice
APA Victorian Transmission System submitted to the AER an annual tariff variation notice for the period 1 January 2025 - 31 December 2025.
Type
Tariff variations
Status
Open
Main Central-West Orana Renewable Energy Zone network project (contestable)
Read our determination on the amounts to be paid to ACEREZ for the main Central-West Orana REZ network project.
Type
Determinations
Status
Open
TasNetworks North West Transmission Developments Stage 1 – Early Works Contingent Project
On 10 October 2024, TasNetworks submitted its contingent project application seeking to increase its revenue to fund early works on NWTD stage 1 early works.
Type
Contingent projects
Status
Open
Power and Water Corporation - Ring Fencing Decision - McArthur River Mining Pipeline
The AER has made a final decision to grant an exemption to Power and Water from their ring-fencing obligations for the McArthur River Mining Pipeline.
Type
Ring-fencing
Status
Current
Origin Retailer of Last Resort Cost Recovery Applications
The AER has approved Origin Energy's six cost recovery applications for costs incurred as the Retailer of Last Resort for retailer failures in 2022.
Type
Cost pass throughs
Status
Current
Transgrid HumeLink contingent project stage 2
Transgrid HumeLink contingent project stage 2
Type
Contingent projects
Status
Current
Waratah Super Battery – Network augmentation and SIPS control system
Read our determination on the costs of the non-contestable Network augmentation and System Integrity Protection Scheme control system component of the WSB project.
Type
Determinations
Status
Current
TasNetworks - Network support pass through 2022-23
TasNetworks - Network support pass through 2022-23
Type
Cost pass throughs
Status
Current
ElectraNet - Network support pass through 2022–23
ElectraNet - Network support pass through 2022–23
Type
Cost pass throughs
Status
Current
Powerlink - Network support pass through 2022–23
Powerlink - Network support pass through 2022–23
Type
Cost pass throughs
Status
Current
Murraylink - Connection charge pass through 2022–23
The AER published its decision on a negative cost pass through application submitted by Murraylink to reduce its 2024-25 allowed revenue due to lower than forecast connection charges in 2022-23.
Type
Cost pass throughs
Status
Current