Results
87 result(s), displaying 1 to 12
APA Victorian Transmission System - 2025 tariff variation notice
APA Victorian Transmission System submitted to the AER an annual tariff variation notice for the period 1 January 2025 - 31 December 2025.
Type
Tariff variations
Status
Open
Power and Water Corporation - Ring Fencing Decision - McArthur River Mining Pipeline
The AER has made a final decision to grant an exemption to Power and Water from their ring-fencing obligations for the McArthur River Mining Pipeline.
Type
Ring-fencing
Status
Current
Murraylink - Connection charge pass through 2022–23
The AER published its decision on a negative cost pass through application submitted by Murraylink to reduce its 2024-25 allowed revenue due to lower than forecast connection charges in 2022-23.
Type
Cost pass throughs
Status
Current
Amadeus Gas Pipeline - 2024–25 tariff variation notice
Amadeus proposed new network prices to apply to its NT gas pipeline for 2024–25.
Type
Tariff variations
Status
Current
AusNet Services - Cost pass through - Easement land tax 2024–25
AusNet Services - Cost pass through - Easement land tax 2024–25
Type
Cost pass throughs
Status
Current
APA Victorian Transmission System - Annual tariff variation 2024
APA Victorian Transmission System submitted to the AER an annual tariff variation notice for the period 1 January 2024 - 31 December 2024.
Type
Tariff variations
Status
Current
Victoria to NSW Interconnector West (VNI West) RIT-T dispute
On 16 October 2023 the AER published a determination clause 5.16B of the National Electricity Rules.
Type
RIT-T and RIT-D disputes
Status
Historical
Amadeus Gas Pipeline - Annual tariff variation 2023–24
Amadeus Gas Pipeline submitted to the AER an annual tariff variation notice for the period 1 July 2023 - 30 June 2024.
Type
Tariff variations
Status
Historical
AusNet Services - Cost pass through - Easement land tax 2023–24
Type
Cost pass throughs
Status
Current
Amadeus Gas Pipeline - Annual tariff variation 2022–23
APA Group submitted to the AER an annual tariff variation for its Northern Territory gas transmission network for the period 1 July 2022 to 30 June 2023.
Type
Tariff variations
Status
Historical
AusNet Services - Cost pass through - Easement land tax 2022–23
Type
Cost pass throughs
Status
Current