TasNetworks North West Transmission Developments Stage 1 – Early Works Contingent Project
On 10 October 2024, TasNetworks submitted its contingent project application seeking to increase its revenue to fund early works on NWTD stage 1 early works.
Type
Contingent projects
Status
Open
Transgrid - Ring-fencing waiver (backup generation) - January 2024
Transgrid submitted a ring-fencing waiver application under clause 5.2 of the Electricity Transmission Ring-fencing Guideline.
Type
Ring-fencing
Status
Open
Victoria: December 2026 - February 2027
The Retailer Reliability Obligation (RRO) is designed to support reliability in the National Electricity Market (NEM).
Type
Retail Reliability Obligation
Status
Open
SA Power Networks - Ring fencing waiver - Market Active Solar Trial - January 2024
SA Power Networks has submitted a waiver application under provision 4.2 of the Ring-fencing Guideline (Electricity distribution)
Type
Ring-fencing
Status
Open
Main Central-West Orana Renewable Energy Zone network project (contestable)
The AER has received a revenue proposal from ACEREZ for the main Central-West Orana REZ network project and has commenced its assessment of the proposal.
Type
Determinations
Status
Open
Essential Energy Bushfire Risk Reclassification Contingent Project
The AER's decision relating to Essential Energy's Bushfire Risk Reclassification Contingent Project
Type
Contingent projects
Status
Open
Ergon Energy Ring-fencing Waiver - Field Services for Powerlink - October 2024
Ergon Energy Network is requesting a ring-fencing waiver in order to provide field services to Powerlink
Type
Ring-fencing
Status
Open
Powerlink Transmission - Determination 2027-2032
The AER will make a determination of the maximum amount of revenue that Powerlink can earn from customers over the period 1 July 2027 to 30 June 2032.
Type
Determinations
Status
Open
AusNet Services Transmission - Determination 2027-2032
The AER will make a determination of the maximum amount of revenue that AusNet Services can earn from customers over the period 1 April 2027 to 31 March 2032.
Type
Determinations
Status
Open
Jemena VEBM cost pass through application
Jemena’s Victorian Emergency Backstop Mechanism (VEBM) cost pass through application
Type
Cost pass throughs
Status
Open
Powercor VEBM cost pass through application
Powercor’s Victorian Emergency Backstop Mechanism (VEBM) cost pass through application
Type
Cost pass throughs
Status
Open
United Energy VEBM cost pass through application
United Energy’s Victorian Emergency Backstop Mechanism (VEBM) cost pass through application
Type
Cost pass throughs
Status
Open