Overview

Sector
Gas
Segment
Distribution
Region
New South Wales
Status
Historical
Commencement date
Regulatory period
AER reference
62669

On 28 February 2019, we released our final decision on the remade decision for Jemena Gas Networks (NSW) Ltd's (JGN) 2015-20 gas access arrangement, commencing 1 July 2015 to 30 June 2020. We also released our final decision adjustment determination for JGN.

Background

In April and June 2015, the AER published final decisions on the 2014-19 distribution determinations for NSW and ACT electricity distributors (Ausgrid, Endeavour Energy, Essential Energy and ActewAGL Distribution), and on the 2015-20 access arrangement for the NSW gas distributor, JGN.

All five businesses sought merits review of the AER’s final decisions. The Public Interest Advocacy Centre (PIAC) also applied for review of the AER’s NSW final decisions. The Commonwealth minister intervened.

The Australian Competition Tribunal handed down its decisions in February 2016 (and March 2016 for JGN). It remitted the decisions to the AER to be remade, in particular in accordance with its orders regarding: the return on debt; the value of imputation credits (gamma); the four electricity distributors’ operating expenditure (and for ActewAGL Distribution, the implications of this for the Service Target Performance Incentive Scheme (STPIS)); and aspects of JGN’s capital expenditure.

In March 2016, the AER sought judicial review of the Tribunal’s decisions on gamma, return on debt and operating expenditure in the Full Federal Court. The Court upheld the AER's appeal in respect of the Tribunal's construction of the rules regarding gamma, but dismissed the appeal in relation to the return on debt and operating expenditures of the electricity businesses.

As a result, was tasked with revisiting its decisions on: the return on debt; the four electricity distributors’ operating expenditure (and for ActewAGL Distribution, the implications of this for the STPIS); and aspects of JGN’s capital expenditure.

Key Documents