AGN is required to submit to the AER for approval a reference service proposal 12 months prior to submission of its access arrangement for the period 1 July 2026 to 30 June 2031. We received AGN's reference service proposal on 1 June 2024.
Under the National Gas Law and the National Gas Rules, the AER has the function of reviewing and approving the terms of AGN's access arrangement proposal (due by 1 July 2025). Interested stakeholders are encouraged to consider the indicative dates for key milestones.
Indicative dates for key milestones in the decision making process
Milestone | Date* |
Reference service proposal due to AER | 1 July 2024 |
AER makes reference service proposal decision | December 2024 |
Access arrangement proposal due to AER | 1 July 2025 |
AER holds stakeholder forum on proposal | Optional |
Stakeholder submissions on proposal close | August 2025 |
AER publish draft decision | November 2025* |
Revised access arrangement proposal due to the AER | January 2026* |
Stakeholder submissions on revised proposal and AER draft decision close | February 2026* |
AER publish final decision | 30 April 2026 |
Please note this timeline is subject to change.
*Date based on AER receiving compliant proposals. May be altered if non-compliant proposals are received.