Overview

Indicative timetable

The AER was required to make an access arrangement final decision to approve or not approve the access arrangement proposal for the APA GasNet Victorian gas transmission system within six months of receipt of the access arrangement proposal. This period can be extended by the AER but must be completed within an absolute overall time limit of 13 months.

The AER is required to follow a prescribed decision making process under the National Gas Rules (NGR) when reviewing APA GasNet’s access arrangement. The following indicative timetable outlines key stages in the review process. It will be updated after each key stage of the review process.

Indicative dates for key milestones in the decision making process
Milestone Date*
Publish proposal 17 April 2012
Submissions on proposal due 18 June 2012
Release of draft decision 10-14 September 2012
Revised proposal to be submitted 9 November 2012
Submissions on revised proposal due January 2013
Release of final decision March 2012

*Please note this timeline is subject to change.