Overview

Indicative timetable

APT Pipelines (NT), for its Amadeus transmission gas pipeline, is required to submit to the AER for approval a reference service proposal 12 months prior to submission of its access arrangement for the period 1 July 2026 to 30 June 2031. We received APT Pipelines (NT)'s reference service proposal on 1 July 2024.

Under the National Gas Law  and the National Gas Rules, the AER has the function of reviewing and approving the terms of the proposal. Interested stakeholders are encouraged to consider the indicative dates for key milestones.

Indicative dates for key milestones in the decision making process

MilestoneDate*
Reference service proposal due to AER1 July 2024
AER makes reference service proposal decisionDecember 2024
Access arrangement proposal due to AER1 July 2025
AER holds stakeholder forum on proposalOptional
Stakeholder submissions on proposal closeAugust 2025
AER publish draft decisionNovember 2025*
Revised access arrangement proposal due to the AERJanuary 2026*
Stakeholder submissions on revised proposal and AER draft decision closeFebruary 2026*
AER publish final decision30 April 2026

Please note this timeline is subject to change.

*Date based on AER receiving compliant proposals. May be altered if non-compliant proposals are received.  

Reference service proposal

APT Pipelines (NT) is required to submit to the AER for approval a reference service proposal 12 months prior to submission of its access arrangement for its Amadeus transmission gas pipeline for the period 1 July 2026 to 30 June 2031 (due by 1 July 2025). We received APT Pipelines (NT)'s reference service proposal on 1 July 2024.

Amadeus 2026-31 - Reference service proposal - 1 July 2024

Download
Authors
APT Pipelines (NT) Pty Limited
Content type
Document

Submissions

Submissions on Amadeus Gas Pipelines' reference service proposal closed on 16 August 2024. We did not receive any submissions.