On 7 December 2018, Evoenergy submitted an application to the AER under clause 6.6.1 of the NER for a positive pass through of costs associated with Evoenergy's compliance with the AER's Electricity Distribution Ring-fencing Guideline.
On 6 February 2019, the AER determined that Evoenergy's application satisfied the definition of a service standard event and a positive change event under the National Electricity Rules. The AER approved a positive pass through amount of $2.05 million ($2018-19) to be recovered from network users in the regulatory years 2019-20 and 2020-21.