On 24 April 2025, the AER published its determination for a positive pass through amount of $15.3 million (nominal, smoothed), to be recovered as follows: $7.5 million in 2025–26 and $7.8 million in 2026–27.
On 24 April 2025, the AER published its determination for a positive pass through amount of $15.3 million (nominal, smoothed), to be recovered as follows: $7.5 million in 2025–26 and $7.8 million in 2026–27.