Application

On 16 December 2022, Energex submitted an application to the AER under clause 6.6.1 (a1)(5) of the National Electricity Rules for a positive pass through of costs related to the 22 February to 7 March 2022 South East Queensland floods. Energex's application proposes to recover $17.03 million from electricity users through an increase in distribution prices in the 2024-25 regulatory year, that is, from 1 July 2024 to 30 June 2025.

Submissions

-

Energy consumers and other interested parties were invited to make submissions on Energex’s 2022 flood event cost pass through application by 10 February 2023.

We did not receive any submissions.