On 19 September 2023, ElectraNet wrote to the AER requesting a determination on its 2022–23 network support pass through application. ElectraNet’s network support pass through application is in relation to the difference between actual network support payments and the forecast network support payment amount for 2022–23 included in ElectraNet’s 2018–23 revenue determination. The AER assessed the application in accordance with clause 6A.7.2(i) of the NER.
The AER determines to approve a positive pass through amount of $10,064,425.