Our review of the version 5 of the Guideline and the Electricity Network Service Provider – Registration Exemption Guideline commenced in May 2021. Our indicative timetable for the review process is outlined below.
Milestone | Date* |
---|---|
Publish consultation paper discussing general concerns identified within both guidelines | May 2021 |
Submissions on the consultation paper close | June 2021 |
Publication of the draft Retail Exempt Selling Guideline, Notice of Draft Instrument, draft AER factsheet and draft Exempt Seller Hardship Policy template | 9 March 2022 |
Public consultation closes – draft Retail Exempt Selling Guideline, draft AER factsheet and draft Exempt Seller Hardship Policy template | 7 April 2022 |
Consultative meetings with stakeholders, upon request | April-May 2022 |
AER publishes final Retail Exempt Selling Guideline, Notice of Final Instrument, AER factsheet and Exempt Seller Hardship Policy template | 15 July 2022 |
AER publishes draft Network Exemptions Guideline and Notice of Draft | August 2022 |
Public consultation – draft Network Exemptions Guideline | September 2022 |
Consultative meetings with stakeholders, upon request | October 2022 |
AER publishes final Network Exemptions Guideline and Reasons for Decision | TBA following consultation |
*Dates are indicative and may change.