On 28 June 2019, the AER received an access arrangement proposal from Jemena Gas Networks (NSW) Ltd (JGN) for its NSW gas distribution network for the period 1 July 2020 to 30 June 2025. On 9 January 2020, JGN submitted its access arrangement revised proposal. Under the National Gas Law and the National Gas Rules, the AER has the function of reviewing and approving the terms of the proposal. Interested stakeholders are encouraged to consider the indicative dates for key milestones.
Milestone | Date* |
---|---|
JGN to submit access arrangement proposal (due date) | 30 June 2019 |
Stakeholder forum on JGN access arrangement proposal | 7 August 2019 |
Stakeholder submissions on JGN access arrangement proposal close | 9 August 2019 |
AER to publish draft decision | 25 November 2019 |
JGN to submit revised access arrangement proposal (due date) | 13 January 2020 |
Stakeholder submissions on JGN revised access arrangement proposal and AER draft decision close | 17 February 2020 |
AER to publish final decision | 5 June 2020 |
*Please note this timeline is subject to change.