On 16 April 2002 ElectraNet SA lodged a revenue cap application (including an NECG report on WACC) for a period of 5 ½ years from 1 January 2003 to 30 June 2008. On 9 May 2002 ElectraNet SA made a supplementary submission in relation to easement value as part of its application.
Regulatory proposal
NECG Analysis of the weighted average cost of capital for ElectraNet SA - 11 April 2002
Download
Content type
Document
Submissions - to ElectraNet SA revenue cap application
Conservation Council of South Australia submission on ElectraNet application - 22 May 2002
Download
Content type
Document
Electricity Consumers Coalition of South Australia submission on ElectraNet application - May 2002
Download
Content type
Document
WMC Copper Uranium submission on ElectraNet application - 23 May 2002
Download
Content type
Document
Submissions - ElectraNet SA response to submissions
Regulatory proposal - ACCC correspondance on cost pass through
ElectraNet wrote to the ACCC seeking advice regarding costs that could be passed through to customers under its revenue cap.
ACCC response regarding ElectraNet's Cost Pass Through Application - 30 January 2002
Download
Content type
Document
ACCC response regarding ElectraNet's proposed tariff statement 2001-02 - 19 June 2002
Download
Content type
Document
Consultant reports - ACCC Consultant reports
As part of the ACCC's revenue cap decision making process for ElectraNet SA, Meritec was engaged to conduct a review that analysed and commented on the proposed opening asset value, capital expenditure and operation and maintenance expenditure.
Submissions - to ACCC Consultant's reports
Submissions received in response to Meritec's reports analysing ElectraNet’s proposed opening asset value, capital expenditure and operation and maintenance expenditure.
BHP-Billiton Petroleum/ECCSA submission on energy transmission easements - July 2002
Download
Content type
Document
ECCSA Comments on consultant reports and ElectraNet comments - August 2002
Download
Content type
Document
Gasnet Australia Comment on WACC proposals for BHP Billiton - June 2002
Download
Content type
Document
NRG Flinders submission on capital expenditure report - 13 August 2002
Download
Content type
Document
Transend submission on operational expenditure report - 19 August 2002
Download
Content type
Document
TransEnergie submission on capital expenditure report - 9 August 2002
Download
Content type
Document
Submissions - ElectraNet SA response to ACCC Consultant reports
ElectraNet response to Meritec capital expenditure report - August 2002
Download
Content type
Document
ElectraNet response to Mercitec operational expenditure report - August 2002
Download
Content type
Document
Submissions - from the Electricity Supply Industry Planning Council
In September 2002 the Electricity Supply Industry Planning Council wrote to the ACCC regarding the capital expenditure program proposed by ElectraNet.