On 28 April 2004, the ACCC approved the release of its draft revenue cap decision for EnergyAustralia.
Draft determination
ACCC - Draft revenue cap decision for EnergyAustralia - 28 April 2004
Stakeholder forum
On 18 June 2004, the ACCC held a public forum so that interested parties could state their views on the draft revenue cap decision for EnergyAustralia.
Joint customer group - Presentation slides for stakeholder forum - Part 1 - 18 June 2004
Joint customer group - Presentation slides for public forum - Part 2 - 18 June 2004
Submissions - to Draft decision
The ACCC invited submissions from interested parties on its draft revenue cap decision for EnergyAustralia.
EnergyAustralia - Attachment 1 to submission to draft decision - NECG report - 2 July 2004
EnergyAustralia - Attachment 2 to submission to draft decision - SKM report - 2 July 2004
EnergyAustralia - Attachment 3 to submission to draft decision - Beresfield DM scoping study - 2 July 2004
EnergyAustralia - Attachment 4 to submission to draft decision - Beresfield regulatory test - 2 July 2004
EnergyAustralia - Attachment 5 to submission to draft decision - Additional feeder bays for Campbell Street - 2 July 2004
Energy market reform forum - Submission to draft decision - 19 July 2004
Revised proposal
On 29 October 2004, EnergyAustralia resubmitted its transmission revenue cap application in response to the ACCC's proposed regulatory framework. The revised application relates only to transmission capital expenditure from 1 July 2004 to 30 June 2009.
Consultant reports - on revised capital expenditure application
The ACCC engaged PB Associates to provide expert advice to assist the ACCC to set a revenue cap for EnergyAustralia. On 17 December 2004, PB Associates completed its report on EnergyAustralia's revised capex application.
PB Associates - Report on EnergyAustralia's revised capex application - 17 December 2004
Submissions - on revised capital expenditure application
On 8 November 2004, the ACCC called for interested parties to make submissions on EnergyAustralia's revised capital expenditure. On 17 December 2004, the ACCC also called for interested parties to make submissions to PB Associates' report on EnergyAustralia's revised capital expenditure proposal.
EnergyAustralia - Submission to consultant report on revised capex application - 14 January 2005
EMRF - Submission to EnergyAustralia's revised capex application - 21 January 2005
EUAA - Submission to EnergyAustralia's revised capex application - 24 January 2005
Draft determination - Supplementary draft decision
On 3 March 2005, the ACCC released its supplementary draft decision for EnergyAustralia's capital expenditure application for the regulatory period 2004/05 to 2008/09.
ACCC - Supplementary draft decision for EnergyAustralia - 3 March 2005
Stakeholder forum - on the Supplementary draft decision
On 18 March 2005, the ACCC held a public forum in Sydney so that interested parties could state their views on the supplementary draft decision for EnergyAustralia's capital expenditure application for the regulatory period 2004 to 2009.
EnergyAustralia - Presentation slides for stakeholder forum - 18 March 2005
ElectraNet - Presentation slides for stakeholder forum - 18 March 2005
Powerlink - Presentation slides for stakeholder forum - 18 March 2005
Submissions - to Supplementary draft decision
The ACCC called for interested parties to make submissions to the ACCC's supplementary draft decision on EnergyAustralia's capital expenditure application for the regulatory period 2004/05 to 2008/09.