On 18 April 2012, ClimateWorks Australia, Seed Advisory and the Property Council of Australia submitted a rule change request to the Australian Energy Market Commission (AEMC) in relation to the process for connecting embedded generators to the distribution network under Chapter 5 of the National Electricity Rules (NER).
Consultation paper