Overview

Sector
Electricity
Segment
Transmission
Region
Tasmania
Status
Historical
Commencement date
Effective date
AER reference
AER213581

On 1 September 2021, TasNetworks wrote to the AER requesting a determination on its 2020–21 network support pass through application. TasNetworks’ network support pass through application is in relation to the difference between actual network support payment and the forecast network support payment amount for 2020–21 included in TasNetworks 2019–24 revenue determination. The AER assessed the application in accordance with clause 6A.7.2(i) of the NER.

On 17 November 2021, the Australian Energy Regulator (AER) published its determination to approve a positive pass through amount of $731,462.