On 20 September 2019, Murraylink wrote to the AER requesting a determination on its 2018-19 connection charge pass through application. The AER assessed the application in accordance with clause 6A.7.3 of the NER.

On 15 November 2019, the AER published its determination to approve a negative pass through amount of $459 184.