Overview

Engagements
Accepting submissions
Sector
Electricity
Segment
Distribution
Region
South Australia
Status
Open
Commencement date
Regulatory period
-
AER reference
AER213704

AER draft decision and SA Power Networks' revised proposal

On 27 September 2024, we released our draft decision for SA Power Networks initial proposal. We held a public forum on our draft decision on 14 October 2024. On 2 December SA Power Networks submitted its revised proposal.

Interested stakeholders are invited to make a submission on our draft decision and the revised proposal by 17 January 2025. Submissions should be sent to SAPN2025ataer [dot] gov [dot] au (SAPN2025[at]aer[dot]gov[dot]au) 

SA Power Networks' proposal

On 31 January 2024 SA Power Networks submitted its 2025–30 Regulatory Proposal. We published an Issues Paper on 26 March 2024 and held a public forum on 9 April 2024. 

Stakeholder submissions on SA Power Networks 2025–30 Regulatory Proposal and our Issues Paper closed on 15 May 2024.

Background

SA Power Networks (SAPN) is an electricity distribution network service provider. 

Under the National Electricity Rules (NER) SAPN must submit an electricity distribution revenue proposal for the next five year regulatory control period commencing 1 July 2025 to 30 June 2030 (2025-30) to the AER by 31 January 2024.

Prior to this, the NER required us to review the current Framework and approach paper that applies to SA Power Networks for the 2025–30 period and decide whether to amend or replace it. On 3 July 2023 the AER published the final Framework and Approach for SA Power Networks.

Key Documents

SAPN - 2025-30 Regulatory Proposal Overview - January 2024

Download
Authors
SA Power Networks (SAPN)
Content type
Document

SAPN - 2025-30 Revised Regulatory Proposal Overview - December 2024

Download
Authors
SA Power Networks (SAPN)
Content type
Document