On 30 April 2019, the AER wrote to Evoenergy advising that it was extending the time period to assess its annual tariff variation notice, pursuant to clause 7.22 of ActewAGL's 2016-20 Access Arrangement. The purpose of the extension is to allow the AER to obtain and assess further information it was has requested from Evoenergy. The AER must now complete its assessment of Evoenergy's 2019-20 tariff variation notice by 29 May 2019 (instead of 1 May 2019).
On 15 May 2019, Evoenergy provided the further information requested by the AER. These documents are available on our website, marked as 'revised'.
Decision
On 29 May 2019, the AER published the approved 2019-20 tariff variation for Evoenergy.
Background
On 15 March 2019, Evoenergy submitted to the AER an annual tariff variation notice for the ACT, Queanbeyan and Palerang gas distribution network. The tariff variation notice sought to increase 2019-20 network charges for Evoenergy's users from 1 July 2019.