Court decision
Release date
Outcome

The Federal Court judgment is available from the Federal Court of Australia website.

On 28 June 2022, the Federal Court found that Hornsdale Power Reserve Pty Ltd (Hornsdale Power Reserve) breached the National Electricity Rules (NER).

The Federal Court found that Hornsdale Power Reserve contravened clauses 3.8.7A(l), 4.9.8(a) and 4.9.8(d) of the NER between 23 July 2019 and 14 November 2019 as it was unable to provide frequency control ancillary services that complied with:

  • its market ancillary service offers;
  • dispatch instructions it received from AEMO; and
  • the technical characteristics of its ancillary service generating units and ancillary service loads.

The Court ordered by consent that Hornsdale Power Reserve pay a pecuniary penalty of $900,000 and contribute to the AER’s legal costs.