Jemena Gas Networks (JGN) has not submitted an annual tariff variation proposal for 2016–17 tariffs. This is because in February 2016 the Australian Competition Tribunal set aside the AER’s June 2015 access arrangement decision for Jemena Gas Networks.
Instead of a tariff variation proposal, JGN offered an enforceable undertaking which sets out its network tariffs from 1 July 2016. On 16 May 2016 the AER formally accepted JGN’s undertaking. The undertaking will expire on 30 June 2017.
JGN’s undertaking will also oblige JGN to continue to provide network services consistent with the non-price terms and conditions of its 2015–20 gas access arrangement.