Overview

Sector
Electricity
Segment
Distribution
Region
Queensland
Entities
Status
Historical
Commencement date
Regulatory period
-
AER reference
37665

On 6 May 2010, the AER made its final determinations on the regulatory proposals submitted by Energex and Ergon Energy, the Queensland electricity distributors. The determinations cover the regulatory control period 1 July 2010 to 30 June 2015 and set the revenue that each of the Queensland distributors are able to recover for the provision of electricity distribution services.

On 19 May 2011, the Australian Competition Tribunal (the Tribunal) varied the AER's determination. The Tribunal made its orders after a review of the value of imputation credits (gamma), alternative control services (quoted services) and labour cost escalators.

Key Documents

Energex's Regulatory Proposal 2010-15

Download
Authors
ENERGEX
Content type
Document

Energex's Revised Regulatory Proposal 2010-15

Download
Authors
ENERGEX
Content type
Document

Queensland Final Distribution Determination Decision 2010-15

Download
Authors
AER
Content type
Document

Australian Competition Tribunal orders - Energex - 19 May 2011

Download
Authors
Australian Competition Tribunal
Content type
Document

Queensland Draft Distribution Determination Decision 2010-15

Download
Authors
AER
Content type
Document