On 22 August 2014, the AER determined an amount recoverable by AGL of $29,287. The amount is payable by three distribution businesses to AGL within 30 days. Following consultation with affected distribution businesses the amount for payment is split as follows: $14,586 by Jemena Gas Networks (NSW) Ltd, $5,094 by Envestra (SA) and $10,147 by SA Power Networks.
Background
On 8 October 2013 AGL submitted a default retailer of last resort (RoLR) cost recovery application to the AER seeking to recover $49,769.45. The AER sought additional information from AGL. AGL completed this request on 8 April 2014. Submissions from interested stakeholders closed 30 May 2014.