Type
Sector
Electricity
Segment
Transmission
Issue date
AER reference
AC 148/22

The AER has published its draft decision on a revenue proposal received from NSW and ACT electricity transmission network business, Transgrid.

This draft decision marks the mid-point of the AER’s consultation on Transgrid’s proposal. Transgrid will now have until 2 December 2022 to respond to the draft decision in a revised proposal.

Stakeholders are invited to attend an online forum on the draft decision on Wednesday, 12 October 2022.

Submissions on both the AER’s draft decision and Transgrid’s upcoming revised proposal are invited by 20 January 2023.

The AER’s final decision, which will be made by 30 April 2023, will set transmission revenues that will form the baseline for Transgrid’s electricity transmission charges for the 5‑year period starting 1 July 2023 to 30 June 2028.